Continuity of Supply

D2

Manage risks associated with continuity of supply from external sources, including oversight of the wider supply chain/ecosystem.

Improvement Planning

Practices-Outcomes-Metrics (POM)

Representative POMs are described for Continuity of Supply at each level of maturity.

1Initial
  • Practice
    Best endeavours of available personnel.
    Outcome
    There is no visibility of supply risks.
    Metric
    Historical Analysis: # IT supplier incidents
2Basic
  • Practice
    Implement a process to monitor tactical events (short-term dips in availability or quality, unexpected price inflation, etc.) in IT services, the rest of the business and IT suppliers.
    Outcome
    There is some limited visibility of short-term risks.
    Metric
    % of contracts where tactical events are monitored
  • Practice
    Define high-level contingency plans for arranging alternative sources in the event of an order being unfulfilled.
    Outcome
    There is a reduction in time required to arrange alternative sources, if required.
    Metric
    % of outsourced IT services that have contingency plans or alternative service providers in placeHistorical analysis: supplier delivery failures impacting availability
3Intermediate
  • Practice
    Implement a process to monitor medium-term operational events and issues (dependence on single suppliers for specific products, frequent order and specification changes from the rest of the business, recurring product quality issues, etc.).
    Outcome
    There is increased visibility of medium-term operational events and issues.
    Metric
    # of events/issues identified % of contracts where medium-term issues are monitored historical analysis: operational events impacting on business
  • Practice
    Establish arrangements in advance with alternative suppliers for most important products/services which can be activated if required.
    Outcome
    Arrangements are in place to utilize alternative sources at short notice if required for the most important products/services.
    Metric
    % of outsourced IT services that have contingency plans or alternative service providers in placeHistorical analysis: supplier delivery failures impacting availability
4Advanced
  • Practices
    • Ensure that continuity and integrity of supply risk evaluations include addressing strategic objectives, such as information-sharing/collaboration, supplier innovation, evolution of supplier rivals, and the impact of discontinuous innovations.
    • Focus on long-term strategic issues which could potentially impact the rest of the business (e.g. supplier insolvency, key product discontinuation, ineffective information-sharing/collaboration, low supplier innovation, legislative changes, evolution of supplier rivals, etc.).
    Outcomes
    • Continuity and integrity of supply risk evaluations increasingly address more strategic objectives.
    • There is high visibility of longer-term strategic issues.
    Metric
    % of contracts where long-term issues are monitored
  • Practice
    Prepare detailed contingency plans for all products and services to transition to alternative suppliers for all key products/services, should the need arise.
    Outcome
    There are comprehensive contingency plans in place for all products and services to transition to alternative suppliers and a decreased risk of stockouts or service loss.
    Metric
    % of outsourced IT services that have contingency plans or alternative service providers in placeHistorical analysis: supplier delivery failures impacting availability.
5Optimized
  • Practices
    • Continually review risk evaluations relating to supply for effectiveness.
    • These should consider the extended supply chain, as appropriate (including links between IT suppliers).
    Outcomes
    • Continuity and integrity of supply risk evaluations and contingency plans take the supply chain/ecosystem into consideration where appropriate.
    • There is high visibility of inter-supplier issues.
    Metric
    % of contracts where inter-supplier issues are monitored
  • Practice
    Continually review contingency plans including the supply chain/ecosystem considerations, as appropriate.
    Outcome
    Contingency plans review and take the supply chain/ecosystem into consideration where appropriate.
    Metric
    % of outsourced IT services that have contingency plans or alternative service providers in placeHistorical analysis: supplier delivery failures impacting availability