Resourcing

A4

Identify and obtain commitment from all resource managers (internal and external) that they will make resources available for project activities in respect of the skill sets, tools and other resources required on the project.

Improvement Planning

Practices-Outcomes-Metrics (POM)

Representative POMs are described for Resourcing at each level of maturity.

2Basic
  • Practices
    • Complete a list with timings of resources including the skill sets necessary to complete project tasks.
    • Request these from the project team and resource providers (e.g. R & D, marketing, engineering, project staff, and so forth).
    Outcome
    Clear communication of the project needs results in them being more likely to be met satisfactorily.
    Metrics
    • Number of projects without resourcing issues (classified by priority, strategic goal, department etc.).
    • Number of resourcing issues escalated for resolution.
  • Practices
    • Complete a list with timings of skill-sets, tools, and resources necessary to support the execution of the project.
    • Try to satisfy these from within the organization or gain sufficient funding to procure the necessary support.
    Outcome
    Supplementary budget requests (if necessary) are submitted early with a clear explanation of the project's needs requiring additional support.
    Metrics
    • Number of projects without resourcing issues (classified by priority, strategic goal, department etc.).
    • Number of resourcing issues escalated for resolution.
3Intermediate
  • Practice
    Utilize and release resources back to suppliers within agreed time periods and flag any variances as early as possible.
    Outcome
    There is a much higher chance that resources will be available when needed and utilized when available.
    Metric
    Project resource utility.
  • Practice
    Utilize and release resources back to suppliers within agreed time-periods and flag any variances as early as possible.
    Outcome
    There is a much higher chance that resources will be available when needed and utilized when available.
    Metric
    Project resource utility.
4Advanced
  • Practice
    Monitor project schedule progression and keep resource providers aware of any changes.
    Outcome
    Resource utility and effectiveness is enhanced, and under-utilized resources are freed and made available to the organization.
    Metrics
    • Project resource utility.
    • Number of projects delayed or awaiting resources.
  • Practice
    Monitor project schedule progression and keep resource providers aware of any changes.
    Outcomes
    • Resource utility and effectiveness is enhanced.
    • Under-utilized resources are freed and made available to the organization.
    Metrics
    • Project resource utility.
    • Number of projects delayed/awaiting resources.
5Optimized
  • Practice
    Develop and maintain a programme of continuous improvement for the management of project primary resources.
    Outcome
    Industry best practices are used for project resource management.
    Metric
    The number of project resource management innovations.
  • Practice
    Develop and maintain a programme of continuous improvement for the management of project supportive resources.
    Outcome
    Best-known industry practices are used for project resource management.
    Metric
    The number of project resource management innovations.